Project Schedule
| Programming Complete | Design and DSA Approval | Construction Completion (Est.) | FFE and Move-In (Est.) |
|---|---|---|---|
| 04-16-2025 | 02-05-2025 | 02-27-2026 | 02-16-2026 |
Current Status/Phase: Completed
Project Progress Update
This project is an approximately 1,030 SF tenant improvement of the existing Student Career Center (RM 301) in Building A at San Diego City College.
Upcoming Milestones:
- Bid award and board approval: September 11, 2025
- Preconstruction kickoff meeting: October 23, 2025
- Construction kickoff: December 22, 2025
- Project closeout phase: Punch walk with architect was scheduled on January 22, 2026
Project Description
- Approximately 1,030 SF tenant improvement to the existing Student Career Center (RM 301) in Building A at San Diego City College
- Removal of existing non-loadbearing interior partition walls, doors, and suspended ceiling grid
- Installation of new non-loadbearing partition walls, interior storefront, and new suspended ceiling grid
- Minor modifications to existing MEP systems, fire alarm, and fire sprinkler systems to accommodate the reconfigured spaces
Project Map

1313 Park Blvd, San Diego, CA 92101
Project News & Information
Additional resources, articles, and links related to this project will appear here when available. For comprehensive information about Measure HH and all ongoing projects, please explore the Measure HH website.
Project Teams
| General Contractor | All-Source |
| Architect | Domus Studio Architects |
| Structural Engineer | N/A |
| Civil Engineer | N/A |
| Mech./ Elect. Engineer | N/A |
| Executive Const. Manager | Steve Evanco |
Last updated: March 31, 2026