San Diego City College Central Plant Expansion HH-C-006-004

Project Schedule

Programming Complete Design and DSA Approval Construction Completion (Est.) FFE and Move-In (Est.)
June 2026 Design: December 2026
DSA: June 2027
June 2028 August 2028

Project Progress Update

San Diego City College Central Plant Expansion

Project Features

The San Diego City College Central Plant Expansion Project will upgrade the existing central utility systems to support upcoming expansions to A Building and the Saville Theatre, which together add over 90,000 gross square feet to the campus. The purpose of this project is to study, analyze and assess the following:

Project Map

#

1313 Park Blvd, San Diego, CA 92101

Project News & Information

Additional resources, articles, and links related to this project will appear here when available. For comprehensive information about Measure HH and all ongoing projects, please explore the Measure HH website.

Project Teams

General Contractor TBD
Architect TBD
Structural Engineer TBD
Civil Engineer TBD
Mech./ Elect. Engineer MA Engineers
Executive Const. Manager Steve Evanco

 

Last updated: March 31, 2026