San Diego City College Harry West Gym HVAC HH-C-003-003

Project Schedule

Programming Complete Design and DSA Approval Construction Completion (Est.) FFE and Move-In (Est.)
January 12, 2026 Design: July 2026
DSA: October 2026
August 2027 November 2027

Current Status/Phase: DSA Review

Project Progress Update

Shatter-resistant glass film installation was completed in August 2026, and classroom improvements, including mobile whiteboards and protective padding field verification, were completed in September 2026. Bid document development began in late September 2026 and the project team is advancing procurement and construction preparation activities.

Upcoming Milestones:

San Diego City College Harry West Gym HVAC #1  San Diego City College Harry West Gym HVAC #2  San Diego City College Harry West Gym HVAC #3

Project Features

The San Diego City College Harry West Gym HVAC Project includes the installation of a new HVAC system to serve the currently unconditioned gymnasium. Other project features include:

Project Map

#

1313 Park Blvd, San Diego, CA 92101

Project News & Information

Additional resources, articles, and links related to this project will appear here when available. For comprehensive information about Measure HH and all ongoing projects, please explore the Measure HH website.

Project Teams

General Contractor TBD
Architect Joseph Wong Design Assoc.
Structural Engineer BWE
Civil Engineer BWE
Mech./ Elect. Engineer MA Engineers
Executive Const. Manager John Atherton

 