Project Schedule
| Programming Complete | Design and DSA Approval | Construction Completion (Est.) | FFE and Move-In (Est.) |
|---|---|---|---|
| November 2025 | Design: October 2026 DSA Approval: April 2027 |
September 2028 | November 2028 |
Project Progress Update
The 100% Design Development documents were received on June 11 and are currently under review. A pre-application meeting with the Division of the State Architect (DSA) was held on June 16. The finishes presentation, including a project fly-through, was presented on June 25. Swing space in Automotive Room A111 has been completed.
Upcoming Milestones:
- The furniture, fixtures, and equipment (FF&E) procurement and installation activities are ongoing.
- Submit project to DSA October 2026.
Project Features
The San Diego College of Continuing Education Educational Cultural Complex Building Trades Training Center Project will include:
- Complete renovation of existing welding instructional spaces including material preparation and welding booth areas with state-of-the-art equipment and dedicated fume extraction system for improved air quality.
- Demo of the east canopy and construction of approximately 4,500 SF of added teaching space.
- New department reception, classrooms, offices, and storage areas.
- Dedicated spaces for robotics and automated equipment that support future-focused trade instruction.
- Replacement of the roof system in its entirety.
Project Map

4343 Ocean View Blvd, San Diego, CA 92113
Project News & Information
Additional resources, articles, and links related to this project will appear here when available. For comprehensive information about Measure HH and all ongoing projects, please explore the Measure HH website.
Project Teams
| General Contractor | TBD |
| Architect | Delawie |
| Structural Engineer | Junker Gonzalez |
| Civil Engineer | Nasland |
| Mech./ Elect. Engineer | Randall Lamb |
| Executive Const. Manager | Steve Evanco |