San Diego College Of Continuing Education ECC Theatre Renovation

Project Schedule

Programming Complete Design and DSA Approval Construction Completion (Est.) FFE and Move-In (Est.)
February 20, 2023 Design: May 16, 2024
DSA Approval: February 5, 2025
January 29, 2027

June 2027

Current Status/Phase: Under Construction 

Project Progress Update

Active Construction continues at the Theatre. Terrazzo installation in the South Wing has been completed. Structural steel and metal deck installation activities remain ongoing. Terrazzo installation in the East Wing is scheduled to begin in early July. Roof repair work will commence in July. Insulation and drywall installation activities have begun in select areas and will continue as construction progresses.

Live Site Camera

Construction site with scaffolding set up along a cement wall and many tools, storage, and safety barriers set up around the site.

Upcoming Milestones:

Project Photos

RENDORINGS:

Theatre Render Right Side Theatre Render Center Theatre Exterior EntranceTheatre Lobby New Theatre Interior Front Theatre Interior Back Theatre Golden Age Gallery Theatre Flex Space Theatre Lobby New

CONSTRUCTION PROGRESS:

Drone aerial view of ECC theatre under construction.  Drone aerial view of ECC theatre under construction from the front entryway with a large lift vehicle park in front.  Drone aerial view of ECC theatre under construction with new cement deck in place. Theatre June Progress 2 Theatre June Progress 4 Theatre June Progress 7 Theatre June Progress 8 Theatre June Progress 9 Theatre June Progress 12 Theatre June Progress 14 Theatre June Progress 15 Theatre June Progress 16

Project Features

The San Diego College of Continuing Education Educational Cultural Complex Theatre Renovation Project includes:

Project Map

#

4343 Ocean View Blvd, San Diego, CA 92113

Project News & Information

Additional resources, articles, and links related to this project will appear here when available. For comprehensive information about Measure HH and all ongoing projects, please explore the Measure HH website.

Project Teams

Construction Manager PCL
Architect HGA
Structural Engineer DCI
Civil Engineer Kettler Lewick Engineering
Mechanical and Electrical Engineer MA Engineers
Executive Const. Manager Ben Baker

 