San Diego Mesa College Gym Floor Replacement
Project Schedule
| Programming Complete | Design and DSA Approval | Construction Completion (Est.) | FFE and Move-In (Est.) |
|---|---|---|---|
| 07-21-2025 | N/A | 08-2026 | N/A |
Current Status/Phase: Construction
Project Progress Update
Removal and replacement of the existing gymnasium floor and subfloor in Building M-100.
Upcoming Milestones:
- A Notice to Proceed (NTP) for the Asbestos-Containing Materials (ACM) Survey and Inspection has been issued to Ninyo & Moore: September 17, 2025.
- Proposed Summer project pending campus confirmation: October 26, 2025.
- Board meeting approval for KYA Group contract: October 30, 2025.
- Project is currently on hold: January 16, 2025.
- Revising proposal to focus on repairs due January 29, 2026. Work is expected to take approximately 6 to 7 weeks.
- Submittals are currently in progress. Construction to begin on Monday, June 1, 2026.
- Pre-construction meeting is scheduled for May 22, 2026.
- The primary scope of work has been completed. The contractor is currently performing change order work June 26, 2026.
Project Features
- Removal and replacement of the existing gymnasium floor and subfloor in Building M-100
- Sanding of the existing wood floor
- Repair or replacement of any poor or damaged floor sections
- Repainting and restriping of game lines, including:
- NCAA men’s and women’s basketball lines on the main court
- Volleyball lines for one main court and two practice courts
- Lines for six badminton courts
- Installation of a new school logo at center court, measuring 6 feet by 8 feet
- Gymnasium dimensions: 118 feet by 105 feet
- Total of two school logos within the gymnasium
Project Map

7250 Mesa College Dr, San Diego, CA 92111
Project News & Information
Additional resources, articles, and links related to this project will appear here when available. For comprehensive information about Measure HH and all ongoing projects, please explore the Measure HH website.
Project Teams
| General Contractor | KYA Group |
| Architect | Lance Lareau |
| Structural Engineer | N/A |
| Civil Engineer | N/A |
| Mech./ Elect. Engineer | N/A |
| Executive Const. Manager | Jonathan Cruz |
Last updated: June 30, 2026