San Diego Miramar College Montgomery Field Aviation Instructional Center

Project Schedule

Programming Complete Design and DSA Approval Construction Completion (Est.) FFE and Move-In (Est.)
February 27th, 2026 Design: November 1, 2026
DSA: July 1, 2027
August 16, 2028 October 16, 2028

Current Status/Phase:  Design Development

Project Progress Update

The project was awarded at the September 11 Board meeting and a kickoff meeting was held while design meetings progress.

Upcoming Milestones:

Project Features

The Miramar College Montgomery Field Instructional Center Project includes the demolition of the existing 6,300 SF hangar and the construction of approximately 18,000 GSF of new space to support expanded aviation workforce training. The renovated facility will include:

San Diego Miramar College Montgomery Field Aviation Instructional Center Concept Plan

Project Map

San Diego Miramar College Montgomery Field Aviation Instructional Center Map

3873 Kearny Villa Road #120, San Diego, CA 92123

Project News & Information

Additional resources, articles, and links related to this project will appear here when available. For comprehensive information about Measure HH and all ongoing projects, please explore the Measure HH website.

Project Teams

General Contractor Harper Construction Company
Architect CSCA
Structural Engineer BWE
Civil Engineer Kimley Horn
Mech./ Elect. Engineer ELEN Consulting
Executive Const. Manager Steve Evanco

 