San Diego Miramar College A200 TI

Project Schedule

Programming Complete Design and DSA Approval Construction Completion (Est.) FFE and Move-In (Est.)
01-26-2026 04-22-2026 08-11-2026 N/A

Current Status/Phase: Construction Phase

Project Progress Update

Over the next three weeks, the contractor will continue flooring, cubby, and data cabling installation, followed by completion of remaining finish work, data cabling testing, and final touch-up painting by August 7. The Owner Punch Walk is scheduled for August 11, followed by completion of punch list corrections, owner turnover activities, and closeout documentation through August 19.

Upcoming Milestones:

Progress Photos:

miramar_college_a200_ti_1 miramar_college_a200_ti_2 miramar_college_a200_ti_3 

Project Features

Remodel the existing second-floor Police Academy classrooms and offices at Miramar College Building A-200.

Install new interior finishes, including:

Project Map

miramar_college_a200_ti_4

10440 Black Mountain Rd, San Diego, CA 92126

Project News & Information

Additional resources, articles, and links related to this project will appear here when available. For comprehensive information about Measure HH and all ongoing projects, please explore the Measure HH website.

Project Teams

General Contractor All Source Building Group
Architect District
Structural Engineer N/A
Civil Engineer N/A
Mech./ Elect. Engineer N/A
Executive Const. Manager N/A

 

Last updated: July 31, 2026