Bond Measure HH Program Updates
Date: November 24, 2026
To: Chancellor’s Cabinet
From: Dr. Joel L. A. Peterson, Vice Chancellor & Executive Operations Officer
Subject: Bond Program Updates (November 2026)
Prior Week’s Key Accomplishments:
City College:
- “A” Building Expansion: A security systems site visit at the Building D bookstore was held on Nov. 16 to support swing space preparations. An on-site bookstore relocation assessment with JE Moore and a presentation to the college president were held on Nov. 17. A mechanical piping connections assessment and site visit was held on Nov. 19, followed by a site logistics planning meeting on Nov. 20.
- Saville Theatre: An existing fault line desktop study was issued on Nov. 20.
Mesa College:
- Allied Health Building S1 Variable Air Volume (VAV) Replacements: A contract with Automated Controls, Inc. for VAV controls replacement was signed on Nov. 16. A separate contract with ACCO for VAV equipment replacement was routed for approval during the week of Nov. 16.
- Athletics Complex: The Design-Build Entity (DBE) submitted the 50% Design Development (DD) deliverable on Nov. 16. An initial review of the deliverable with the DBE was held on Nov. 17, followed by a cost estimate presentation to the district on Nov. 18. A value engineering session with the DBE was held on Nov. 20.
- Mesa Commons Envelope Leak Mitigation: A preconstruction meeting with campus stakeholders was held on Nov. 18.
- English/Student Support Building: The first monthly steering committee meeting was held on Nov. 18 to present programming workshop findings.
- Performing Arts Center / Administration & Parking Structure: The DBE submitted the 100% DD deliverable during the week of Nov. 16. Stakeholder review meetings were held Nov. 17-20.
Miramar College:
- Heavy Duty Advanced Transportation (C3) Building Roll-Up Door Motor Replacement: The project entered the closeout phase. A punch-list and acceptance walk was held on Nov. 16.
- Early Education Center: A design completion meeting with the DBE and stakeholders was held on Nov. 18.
- Performing Arts Center & English/Gallery Building: The DBE and district held a pre-application meeting with the Division of the State Architect (DSA) on Nov. 18. A DD completion meeting with the DBE and stakeholders was held on Nov. 19.
- Aviation Instructional Center: The architect held a programming meeting with the City of San Diego on Nov. 19 to discuss potential design options.
College of Continuing Education:
- Educational Cultural Complex (ECC) New Facilities Building: A stakeholder design meeting is scheduled for Nov. 20.
- West City Expansion: A stakeholder design meeting is scheduled for Nov. 16.
Other District Locations:
No items to report.
Coming Week Look-Ahead:
City College:
- Hardscape Improvements: Precision Concrete is scheduled to mobilize on Nov. 23.
- Saville Theatre: Landscape and irrigation restoration associated with fault line trenching is scheduled for Nov. 23-27. Tentative boring work in the greenbelt west of the LRC is scheduled for Nov. 24.
Mesa College:
- Athletics Complex: The district will continue its review of the 50% DD deliverable during the week of Nov. 23. Kitchell Estimating will also continue reviewing the corresponding cost estimate.
- Mesa Commons Envelope Leak Mitigation: Construction is scheduled to begin Nov. 23.
- Performing Arts Center / Administration & Parking Structure: A review of the 100% DD deliverable with the district is scheduled for Nov. 23. The district and Kitchell Estimating will continue reviewing the deliverable and corresponding cost estimate during the week of Nov. 23.
- English/Student Support Building: The design team will prepare for the second round of stakeholder workshops.
- Design Center Improvements: A notice to proceed (NTP) for construction is anticipated between Nov. 20 and 23.
Miramar College:
- Aviation Instructional Center: The architect will continue developing three design options for the potential alternative site at Montgomery Field during the week of Nov. 23.
- Early Education Center: The DBE is scheduled to mobilize for Increment 1 during the week of Nov. 23.
- Performing Arts Center & English/Gallery Building: The design team will continue developing the building's exterior design during the week of Nov. 23.
College of Continuing Education:
- ECC Ceramics Renovation: Demolition is scheduled to begin Nov. 23 and continue through Nov. 27.
- Lighting Inverter and Batteries Replacement: A notice of award (NOA) was issued to Ready Electric. An NTP is anticipated during the week of Nov. 23.
Other District Locations:
No items to report.
Key Items of Interest
No items to report.
Upcoming Needed Campus Action Items (Time Sensitive)