Chancellor's Cabinet Report 11-24-26

Bond Measure HH Program Updates

Date: November 24, 2026
To: Chancellor’s Cabinet
From: Dr. Joel L. A. Peterson, Vice Chancellor & Executive Operations Officer
Subject: Bond Program Updates (November 2026)

Prior Week’s Key Accomplishments:

City College:

  1. “A” Building Expansion: A security systems site visit at the Building D bookstore was held on Nov. 16 to support swing space preparations. An on-site bookstore relocation assessment with JE Moore and a presentation to the college president were held on Nov. 17. A mechanical piping connections assessment and site visit was held on Nov. 19, followed by a site logistics planning meeting on Nov. 20.
  2. Saville Theatre: An existing fault line desktop study was issued on Nov. 20.

Mesa College:

  1. Allied Health Building S1 Variable Air Volume (VAV) Replacements: A contract with Automated Controls, Inc. for VAV controls replacement was signed on Nov. 16. A separate contract with ACCO for VAV equipment replacement was routed for approval during the week of Nov. 16.
  2. Athletics Complex: The Design-Build Entity (DBE) submitted the 50% Design Development (DD) deliverable on Nov. 16. An initial review of the deliverable with the DBE was held on Nov. 17, followed by a cost estimate presentation to the district on Nov. 18. A value engineering session with the DBE was held on Nov. 20.
  3. Mesa Commons Envelope Leak Mitigation: A preconstruction meeting with campus stakeholders was held on Nov. 18.
  4. English/Student Support Building: The first monthly steering committee meeting was held on Nov. 18 to present programming workshop findings.
  5. Performing Arts Center / Administration & Parking Structure: The DBE submitted the 100% DD deliverable during the week of Nov. 16. Stakeholder review meetings were held Nov. 17-20.

Miramar College:

  1. Heavy Duty Advanced Transportation (C3) Building Roll-Up Door Motor Replacement: The project entered the closeout phase. A punch-list and acceptance walk was held on Nov. 16.
  2. Early Education Center: A design completion meeting with the DBE and stakeholders was held on Nov. 18.
  3. Performing Arts Center & English/Gallery Building: The DBE and district held a pre-application meeting with the Division of the State Architect (DSA) on Nov. 18. A DD completion meeting with the DBE and stakeholders was held on Nov. 19.
  4. Aviation Instructional Center: The architect held a programming meeting with the City of San Diego on Nov. 19 to discuss potential design options.

College of Continuing Education:

  1. Educational Cultural Complex (ECC) New Facilities Building: A stakeholder design meeting is scheduled for Nov. 20.
  2. West City Expansion: A stakeholder design meeting is scheduled for Nov. 16.

Other District Locations:

No items to report.

Coming Week Look-Ahead:

City College:

  1. Hardscape Improvements: Precision Concrete is scheduled to mobilize on Nov. 23.
  2. Saville Theatre: Landscape and irrigation restoration associated with fault line trenching is scheduled for Nov. 23-27. Tentative boring work in the greenbelt west of the LRC is scheduled for Nov. 24.

Mesa College:

  1. Athletics Complex: The district will continue its review of the 50% DD deliverable during the week of Nov. 23. Kitchell Estimating will also continue reviewing the corresponding cost estimate.
  2. Mesa Commons Envelope Leak Mitigation: Construction is scheduled to begin Nov. 23.
  3. Performing Arts Center / Administration & Parking Structure: A review of the 100% DD deliverable with the district is scheduled for Nov. 23. The district and Kitchell Estimating will continue reviewing the deliverable and corresponding cost estimate during the week of Nov. 23.
  4. English/Student Support Building: The design team will prepare for the second round of stakeholder workshops.
  5. Design Center Improvements: A notice to proceed (NTP) for construction is anticipated between Nov. 20 and 23.

Miramar College:

  1. Aviation Instructional Center: The architect will continue developing three design options for the potential alternative site at Montgomery Field during the week of Nov. 23.
  2. Early Education Center: The DBE is scheduled to mobilize for Increment 1 during the week of Nov. 23.
  3. Performing Arts Center & English/Gallery Building: The design team will continue developing the building's exterior design during the week of Nov. 23.

College of Continuing Education:

  1. ECC Ceramics Renovation: Demolition is scheduled to begin Nov. 23 and continue through Nov. 27.
  2. Lighting Inverter and Batteries Replacement: A notice of award (NOA) was issued to Ready Electric. An NTP is anticipated during the week of Nov. 23.

Other District Locations:

No items to report.

Key Items of Interest

No items to report.

Upcoming Needed Campus Action Items (Time Sensitive)

No items to report.